New Brewery Update: Bring in the Tanks!

We're relocating our spiritual home...


Bring in the tanks!

In 2008, our brewhouse was delivered and assembled in our original site in Byron Bay. A couple of weeks ago and almost 10 years to the day, we switched off the brewhouse at our original site and commenced its decommissioning, in preparation for the move to our new brewery build on Ewingsdale Road, just around the corner.

It will be a staged move, with the brewhouse relocating first, then the 100 hec fermenters from our Murwillumbah brewery and finally the remaining 50 hecs fermenters from our original Byron Bay brewery over the coming months. In between these moves, the builders will be installing the new brew deck and gantry walkways.

Currently onsite at the moment, the tilers have put the final touches to the brew-house tiles, the electrical fit-out is underway and the glazier is installing the windows.

See our new brewery build from above here.

More updates to come...